Contractor pays PGE GiEK 135M PLN in Turów Power Plant block 7 settlement

The contractor for unit 7 at Turów Power Plant paid PGE GiEK 135 million złoty as part of a settlement agreement over the design and construction contract. This resolves a contractual dispute, likely avoiding prolonged litigation. The payment provides financial relief to PGE and clarifies the project's status, though the impact on plant operations is limited.