Chile terminates CESFAM Bahía Mansa contract after 43% build, 2% progress in 57 days

The Osorno Health Service terminated its contract with Standarhouse Ltda. for the CESFAM de Bahía Mansa health center, citing construction delays and two prior extensions. Physical progress stands at 43%, with only 2% advance over the last 57 days, making the delivery date unattainable. The termination underscores persistent infrastructure project failures in Chile's public health sector, though the impact is localized.